August 2016

September 2016

Ian gets to work on restoring the original fireplace (a long process) which had been boxed in by the previous owners. Some more before shots of the bedroom before work starts on fixing it up.

August/September  2017

New Radiator installed from Ribble Radiators and the walls/ceilings are re-skimmed.

Early October 2019

Fireplace Hearth tiles are laid and the Fireplace is finally restored.

Late October 2019

The bedroom is painted, carpets laid and furniture delivered.

November 2019 – Current Time